Please enable JavaScript to view this site.

 

 

This table contains information about the individual PPIs of a case, such as the total case idle time classes between the process start and the process end of the subprocesses. The table contains one row per case per subprocess and one row per case which measures the process lead time from start to end. The table is created automatically by the MPM process mining methods.

 

Field Name

Explanation

CaseStartDate

Start date for a Case and key to the table MasterCalendar.

%CaseID

The field contains the unique case identification.

Subprocess

Partial processes for which the lead time and other time related measures will be calculated.

SubprocessFinished

Flag 0 or 1, if the subprocess is finished or not.

SubprocessStartDate

Start date for a subprocess.

SubprocessEndDate

End date for a subprocess.

CaseLeadTime

Lead Time from start to end.

SubProcessCurrentLeadTime

Displays the current lead time of the subprocess.

TotalCaseEventDuration

The field contains the sum of all activity durations for each case.

TotalCaseIdleTime

The field contains the sum of all waiting times for each case.

CaseLeadTimeClass

All lead times from all cases are used to build Lead Time Classes to show the respective class for this case. Width/number of classes is determined by using the 75%/25% quantiles of the lead time.

CaseEventDurationClass

Class for the sum of event durations per Case (similar to CaseLeadTimeClass).

CaseIdleTimeClass

Class for the sum of waiting times per Case (similar to CaseLeadTimeClass).

SubprocessTargetTimeMissed

Flag 0 or 1, if the subprocess target time is missed or not.

SubprocessTargetTime

Indicates the subprocess target time.

SubprocessTargetTimeOperator

Specifies whether the subprocess target time is a desired upper or lower limit.

SubprocessStartTime

The start time of the subprocess.

SubprocessEndTime

The end time of the subprocess.

.

 

 

 